COMMITMENTS AND CONTINGENCIES |
9 Months Ended |
---|---|
Sep. 30, 2017 | |
Commitments and Contingencies Disclosure [Abstract] | Ìý |
COMMITMENTS AND CONTINGENCIES |
NOTE 18 - COMMITMENTS AND CONTINGENCIES
Contingencies
We are currently the subject of, or party to, various claims and legal proceedings incidental to our operations. If management believes that a loss arising from these matters is probable and can reasonably be estimated, we record the amount of the loss or the minimum estimated liability when the loss is estimated using a range, and no point within the range is more probable than another. As additional information becomes available, any potential liability related to these matters is assessed and the estimates are revised, if necessary. Based on currently available information, management believes that the ultimate outcome of these matters, individually and in the aggregate, will not have a material effect on our financial position, results of operations or cash flows. However, these claims and legal proceedings are subject to inherent uncertainties and unfavorable rulings could occur. An unfavorable ruling could include monetary damages, additional funding requirements or an injunction. If an unfavorable ruling were to occur, there exists the possibility of a material impact on the financial position and results of operations for the period in which the ruling occurs or future periods. However, we do not believe that any pending claims or legal proceedings will result in a material liability in relation to our consolidated financial statements.
Currently, we have recorded a liability in the Statements of Unaudited Condensed Consolidated Financial Position related to the following legal matters:
Michigan Electricity Matters. On February 19, 2015, in connection with various proceedings before FERC with respect to certain cost allocations for continued operation of the Presque Isle Power Plant in Marquette, Michigan, FERC issued an order directing MISO to submit a revised methodology for allocating SSR costs that identified the load serving entities that require the operation of SSR units at the power plant for reliability purposes.Ìý On September 17, 2015, FERC issued an order conditionally approving MISO’s revised allocation methodology. On September 22, 2016, FERC denied requests for rehearing of the February 19 order, rejecting arguments that FERC did not have the authority to order refunds in a cost allocation case and to impose retroactive surcharges to effectuate such refunds. FERC, however, suspended any refunds and surcharges pending its review of a July 25, 2016 ALJ initial decision on the appropriate amount of SSR compensation. Should FERC award SSR costs based on retroactive surcharges and the amount of SSR compensation not be adjusted, our current estimate of the potential liability to the Empire and Tilden mines is $13.6 million, based on MISO's June 14, 2016 refund report (as revised in MISO's July 20, 2016 errata refund report) for the Escanaba, White Pine and Presque Isle SSRs.Ìý On November 8, 2016, Tilden and Empire, along with various Michigan-aligned parties, filed petitions for review of FERC’s order regarding allocation and non-cost SSR issues with the U.S. Court of Appeals for the D.C. Circuit. On January 27, 2017, Tilden, Empire and other appellants filed a motion to terminate further abeyance of briefing so that cost allocation issues could be heard earlier at the Court of Appeals than revenue requirement issues still pending at FERC, which motion was granted on April 4, 2017. We will continue to vigorously challenge both the amount of the SSR compensation and the imposition of any SSR costs before FERC and the U.S. Court of Appeals for the D.C. Circuit. As of SeptemberÌý30, 2017, $13.6 million is included in our Statements of Unaudited Condensed Consolidated Financial Position as part of Accrued expenses.
CCAA Proceedings
In January 2015, the Bloom Lake Group commenced CCAA proceedings. Effective January 27, 2015, following the CCAA filing of the Bloom Lake Group, we deconsolidated the Bloom Lake Group and certain other wholly-owned subsidiaries comprising substantially all of our Canadian operations. Additionally, on May 20, 2015, the Wabush Group commenced CCAA proceedings which resulted in the deconsolidation of the remaining Wabush Group entities that were not previously deconsolidated. As a result of this action, the CCAA protections granted to the Bloom Lake Group were extended to include the Wabush Group to facilitate the reorganization or divestiture of each of their businesses and operations.
Prior to the deconsolidations, various Cliffs wholly-owned entities made loans to the Canadian Entities for the purpose of funding their operations and had accounts receivable generated in the ordinary course of business. The loans, corresponding interest and the accounts receivable were considered intercompany transactions and eliminated from our consolidated financial statements. Since the deconsolidations, the loans, associated interest and accounts receivable are considered related party transactions and have been recognized in our consolidated financial statements at their estimated fair value of $51.9 million and $48.6 million classified as Loans to and accounts receivable from the Canadian Entities in the Statements of Unaudited Condensed Consolidated Financial Position as of SeptemberÌý30, 2017 and DecemberÌý31, 2016, respectively.
During the three months ended June 30, 2017, we became aware that it was probable the Monitor will assert a preference claim of the CCAA estate against the Company. Given that it is probable the claim will be asserted by the Monitor, we have recorded an estimated liability approximately equal to the value of the Company’s related-party claims against the CCAA estate of $50.0 million, classified as Contingent claims in the Statements of Unaudited Condensed Consolidated Financial Position as of SeptemberÌý30, 2017 and included within Income (Loss) from Discontinued Operations, net of tax in the Statements of Unaudited Condensed Consolidated Operations for the nine months ended SeptemberÌý30, 2017. Should the Monitor proceed to assert the claim, we believe the Monitor will demand an amount in excess of the value of Cliffs’ related-party claims against the estate. Thus, it is possible that a change in the estimated liability may occur in the future. Cliffs denies it is liable for any amount and will vigorously defend such claim.
We previously recorded liabilities of $37.2 million related to guarantees for certain environmental obligations of the Canadian Entities, classified as Other liabilities in the Statements of Unaudited Condensed Consolidated Financial Position as of DecemberÌý31, 2016. During the three months ended SeptemberÌý30, 2017, the Wabush Scully Mine was sold as part of the ongoing CCAA proceedings. As part of the sale, the environmental remediation obligations were conveyed to the buyer and we were released from our guarantees, which resulted in a net gain of $31.4 million included in Income (Loss) from Discontinued Operations, net of tax in the Statements of Unaudited Condensed Consolidated Operations.
As of SeptemberÌý30, 2017, substantially all of the assets available to the estate have been liquidated. The CCAA proceedings are still ongoing and the Monitor is evaluating all claims into the estate including our related-party claims. Currently, there is uncertainty as to the amount of the distribution that will be made to the creditors of the estate, including, if any, to Cliffs, and whether Cliffs could be held liable for claims that may be asserted by or on behalf of the Bloom Lake Group or the Wabush Group or by their respective representatives against non-debtor affiliates of the Bloom Lake Group and the Wabush Group.
After payment of sale expenses, taxes and repayment of the DIP financing, the net proceeds from the liquidation of assets and certain other divestitures by the Canadian Entities are currently being held by the Monitor, on behalf of the Canadian Entities, to fund the costs of the CCAA proceedings and for eventual distribution to creditors of the Canadian Entities pending further order of the Montreal Court.
|